Project Management

101 flashcards by MentisLibrary

Scope, schedule, cost, risk, and the earned value maths that tells you which one is slipping. Covers the PMP vocabulary alongside Scrum and Kanban, and flags the traps that quietly sink projects.

What is a project?
A temporary endeavor undertaken to create a unique product, service, or result
What distinguishes a project from operations?
A project is temporary and produces something unique; operations are ongoing and repetitive
What is a program in project management?
A group of related projects managed together to obtain benefits not available from managing them individually
What is a portfolio in project management?
A collection of projects, programs, and operations grouped together to achieve strategic objectives, not necessarily interdependent
What are the five process groups in the PMBOK Guide?
Initiating, Planning, Executing, Monitoring and Controlling, and Closing
What is a project charter?
The document that formally authorizes a project, names the project manager, and states high level objectives, scope, and constraints
What is a project sponsor?
The senior individual who funds the project, owns the business case, and clears organizational obstacles
What is a stakeholder?
Any individual or group that can affect, be affected by, or perceive itself to be affected by the project
What is a stakeholder register?
A document listing stakeholders with their interests, influence, expectations, and communication needs
What is a power interest grid?
A stakeholder mapping tool plotting influence against interest to decide engagement level: manage closely, keep satisfied, keep informed, or monitor
What is scope in project management?
The sum of the products, services, and results to be provided by the project, and the work required to deliver them
What is the difference between product scope and project scope?
Product scope is the features and functions of the deliverable; project scope is the work needed to deliver it
What is a scope statement?
A written description of the project deliverables, acceptance criteria, exclusions, assumptions, and constraints
What is scope creep?
The uncontrolled expansion of project scope without adjustments to time, cost, and resources
What is gold plating?
Delivering more than the requirements ask for, on the team's own initiative and without authorization
What is a work breakdown structure, or WBS?
A hierarchical decomposition of the total scope of work into smaller, manageable deliverables
What is a work package?
The lowest level component of the WBS, small enough to be estimated, scheduled, and assigned to one owner
What is the 100 percent rule in a WBS?
The WBS must include 100 percent of the work defined by the scope, and no more
What is a WBS dictionary?
A companion document giving detail for each WBS element: description, deliverables, acceptance criteria, owner, and estimates
What is the triple constraint?
The interdependent limits of scope, time, and cost, with quality affected by any change to them
What is a milestone?
A significant point or event in a project, with zero duration
What is the critical path?
The longest sequence of dependent activities through a project, determining the shortest possible project duration
What is float or slack?
The amount of time an activity can be delayed without delaying the project or a successor
What is the difference between total float and free float?
Total float is delay possible without delaying the project end; free float is delay possible without delaying any successor activity
What is the critical path method, or CPM?
A schedule analysis technique that calculates early and late start and finish dates through a forward and backward pass to find the critical path and float
What is PERT?
Program Evaluation and Review Technique, a schedule method using three point estimates to model uncertainty in activity duration
What is the PERT three point estimate formula?
Expected duration equals optimistic plus four times most likely plus pessimistic, divided by six
What is a Gantt chart?
A bar chart showing activities against a calendar, with bar length representing duration and links representing dependencies
What is a network diagram?
A schematic showing project activities and their logical dependencies as nodes and arrows
What are the four dependency types?
Finish to start, start to start, finish to finish, and start to finish